Letter of award
A letter of award, also known as an award letter, is sent by a client/employer as written confirmation that a tenderer has been successful and will be awarded a contract.
The letter forms part of the contract award, which is the process of formally notifying a tenderer that they have been selected as the supplier for a particular contract. It will usually be sent out together with letters to unsuccessful tenderers.
The letter will typically contain details of the amount of the award, the date of the award, and when the contract will be signed. A notice to proceed may also be included detailing the date on which a contractor may begin work.
On public projects, the despatch of a letter of award signifies the start of the Alcatel (standstill) period in the procurement process. This allows unsuccessful tenderers the chance to obtain more information on the award of the contract so they can take appropriate action if they believe they have been unfairly treated.
As such it may be necessary for a letter of award to avoid committing to accepting the tender, since this can be taken to be binding. Rather, the aim of the letter is to give the successful bidder reassurance, and to allow them to begin preparations, whilst refraining from any commitment to legally binding obligations.
As a result, a letter of award may be referred as a 'letter of intent to award' or it may include caveats.
NB A letter of intent is a document expressing an intention to enter into a contract at a future date but creating no contractual relationship until that future contract has been entered into. This may be necessary when suppliers are incurring costs and overheads and can be used as an interim arrangement prior to a formal contract being executed. For more information see: Letter of intent.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.